Completed Phases

Resource Development CompletedPre-Engineering/Study CompletedEngineering Not Yet CompletedBidding Not Yet CompletedRight-of-Way Not Yet CompletedConstruction Not Yet CompletedRestoration Not Yet Completed

Current Phase

Engineering & Design

Length

.63 Miles

Project Owner

The City of Fort Wayne, Fort Wayne City Utilities

Project Description

The section of the Rivergreenway along the Maumee River just east of Coliseum Blvd, adjacent to the former Lakeside Golf Course will be moved to the north and rerouted away from the river due to flooding issues and eroding riverbank. Notice to proceed was given to Earth Source in late December 2023. Meetings with design firm have begun in May. Wetland delineation completed. Meetings with consultant and INDOT complete. Some slight revisions to alignment have been made and chose three sites for park benches and overlooks.

Project is set to be bid in the fall of 2025. Waiting on federal and state agency approvals and permits.