Completed Phases

Resource Development CompletedPre-Engineering/Study CompletedEngineering Not Yet CompletedBidding Not Yet CompletedRight-of-Way Not Yet CompletedConstruction Not Yet CompletedRestoration Not Yet Completed

Current Phase

Pre-Engineering/Study

Length

1.03 Miles

Project Owner

City of Fort Wayne Public Works

Project Description

This is phase 2 of a 2-phase projectThis trail will be an extension of the Maplecrest Road Trail north to St. Joe Center Rd. 8-10ft wide trail will run along the north side of Stellhorn Road from the entrance of Northwood Plaza by Pizza Hut to the AEP transmission line by Eicher Drive. The trail will then run north along the AEP transmission line to the YMCA and St Joe Center Road. This project planned on using a service road that AEP had planned on building during their transmission project on this corridor. AEP is wrapping up their transmission project in October. Survey work has been ordered with design planned to begin in 2025.