Completed Phases

Resource Development CompletedPre-Engineering/Study CompletedEngineering Not Yet CompletedBidding Not Yet CompletedRight-of-Way Not Yet CompletedConstruction Not Yet CompletedRestoration Not Yet Completed

Current Phase

Right-Of-Way Acquisition

Length

1.12 Miles

Project Owner

City of Fort Wayne Public Works

Project Description

This is phase 1 of a 2-phase projectThis trail will be an 8-10 foot trail connecting from the Jackson R. Lehman YMCA to just north of Bridlewood Dr on Maplecrest Road.

Received 95% plans and engineer’s estimates on 5/9/25. Beginning appraisal problem analysis and then appraising. Buying ROW could begin in January for 25 parcels (three of which will be donated.)