Completed Phases
Current Phase
Pre-Engineering/Study
Length
2.82 Miles
Project Owner
City of Fort Wayne and Allen County and NIRCC
Project Description
Road widening project from north of Auburn Road to Mayhew/ Tonkle. The trail will be on the east side and sidewalk on the west side. This project will likely be bid in three phases. Stage 1 drawings are complete. Negotiations are underway. Notice to proceed this fall. NEPA Environmental Study is underway and engineering has begun.
The estimated phase timeline, phase 1 in 2027, phase 2 2028/2029, phase 3 timeline is unknown at this time.
Public information meeting was held 7/31/25.