Completed Phases

Resource Development Not Yet CompletedPre-Engineering/Study Not Yet CompletedEngineering Not Yet CompletedBidding Not Yet CompletedRight-of-Way CompletedConstruction Not Yet CompletedRestoration Not Yet Completed

Current Phase

Engineering & Design

Length

.32 Miles

Project Owner

City of Fort Wayne Public Works

Project Description

 Trail from Coliseum Blvd to Reed Road. Concordia Lutheran Church and School has already constructed .13 miles of the trail. The City will construct the trail on the north side of Lake Ave completing the two sections east and west of the existing trail. Working on the right-of-way acquisition. Survey work was completed in June. Preliminary drafting is completed. Work continues on design.