Completed Phases

Resource Development Not Yet CompletedPre-Engineering/Study Not Yet CompletedEngineering Not Yet CompletedBidding Not Yet CompletedRight-of-Way Not Yet CompletedConstruction Not Yet CompletedRestoration Not Yet Completed

Current Phase

Engineering & Design

Length

.23 Miles

Project Owner

City of Fort Wayne Public Works

Project Description

 The Rivergreenway currently share the road with parking on both sides. Trail will be built on the west side of the St. Mary’s River, eliminating the need to use Juliette Ave. City Utilities recently completed the trail between Brown St and Hale Ave as part of another project. Right-of-way acquisition is underway. Preliminary trail alignment is complete. Survey work is complete. The City is meeting with property owners and has sent letters to all of the property owners to seek input on trail alignment.