Complete
Length
.7 Miles
Project Owner
Leo-Cedarville, NewAllen Alliance, Fort Wayne Trails Inc
Project Description
A 10′ wide trail on the south side of Hosler Rd, will cross to the north side at St Rd. 1 to Grabill Bridge. A separate bridge upgrade will include a cantilevered trail addition on the north side of Grabill Bridge. This is part of the NewAllen Alliance Stellar Portfolio from 2019-2023. The preliminary design is complete and property acquisition is complete. The project was bid in November 2024 and the Allen County Commissioners approved an ARPA grant for 1.125 Million with a successful County Council vote.
The Bridge is currently under construction and the trail from Amstutz to IN-1 is complete.
Last Updated
October 2025