Completed Phases

Resource Development Not Yet CompletedPre-Engineering/Study Not Yet CompletedEngineering Not Yet CompletedBidding Not Yet CompletedRight-of-Way Not Yet CompletedConstruction Not Yet CompletedRestoration Not Yet Completed

Current Phase

Engineering & Design

Length

1.8 Miles

Project Owner

City of Fort Wayne Public Works, Redevelopment Commission

Project Description

Project limits will be from east of Maplecrest Road to west of Wheelock Road on the north side. City has received 30% plans. The city walked the trail corridor with DLZ on 9/30. Utility coordination has begun. City has reviewed and given feedback on some design alternatives at several locations. Met with DLZ and a property owner in December 2024.

Engineering continues, 60% plans were presented and reviewed by the City in June. Utility coordination will now begin.

Met with Utility Companies 9/12/25.