Completed Phases

Resource Development CompletedPre-Engineering/Study CompletedEngineering CompletedBidding Not Yet CompletedRight-of-Way CompletedConstruction Not Yet CompletedRestoration Not Yet Completed

Current Phase

Resource Development

Length

.5 Miles

Project Owner

Allen County

Project Description

12′ wide trail from Fitch Rd to the DeKalb County Line following Fitch Rd and County Rd 9A. The project is designed and all right of way is complete. Funding budgeted for 2024 was needed for another project. Funding may be available in 2025. On hold until DeKalb decides on alignment.

Last Updated

October 2025